Bienvenido! Acabas de iniciar session
You have been logged out due to inactivity
Introduzca la dirección de correo electrónico que utilizó para crear la cuenta. Le enviaremos un enlace que le permitirá crear una nueva contraseña.
Por favor revise su correo electrónico. Haga clic en el enlace en el correo electrónico para crear una nueva contraseña.
¡Éxito! Su contraseña ha sido actualizada.
¡Éxito! Su contraseña ha sido actualizada.
The following are all the IBC Category D,E,F2 Code Requirements for lay-in acoustical panels and direct-hung acoustical tiles.
Basic Connections, Perimeter, and Lateral Splay Bracing | Requirements |
Minimum intersection strength limits @ MT / CT | 180 lbs |
Vertical hanger wire 12-gauge @ 4' o.c. | Required |
Connection device from vertical wire to the structure above must sustain min 100 lbs | Required |
Main tee classifications | Heavy-duty |
1 in 6 max plumb of vertical hanger wires | Required |
Perimeter vertical hanger wires not more than 8" from wall | Required |
Grid end/wall clearance | Min 3/4" |
Perimeter closure (molding) width | Min 2 " |
Grid connection to perimeter attached on two adjacent walls | Required |
Perimeter tee ends tied together | Required |
Horizontal restraint (splay wires or rigid bracing) within 2" of intersection and splayed 90° apart at 45° angles | Required |
Compression posts (struts) 12' o.c. in both directions, starting 6' from walls | Required |
Splay bracing connection strength 200 lbs or the design load, whichever is greater | Required |
Partition attachment | Bracing independent of ceiling splay bracing |
Seismic separation joint4 | Required for areas > 2,500 sq. ft. (or full height partition) |
Rigid bracing for ceiling plane elevation changes | Required |
Light Fixture Attachment | Requirements |
Light fixture (all types) mechanically attached to grid NEC 410-16 (two per fixture unless independently supported) | Required |
Surface-mounted fixtures attached to grid | Not required |
Pendant-hung fixtures directly supported from structure with 9-gauge wire (or approved alternative) | Required |
Rigid lay-in or can light fixtures | |
≤ 10 lbs – one wire to structure (may be slack) | Required |
11 to 56 lbs – two wires from housing to structure (may be slack) | Required |
≥ 57 lbs – supported directly to structure by approved | Required |
Light Fixture Supplementary Hanger Wires | Requirements |
Intermediate Duty Main Tees with cross tee rating below 16 lbs./LF | Required |
Min. 12-gauge hanger wires must be attached to the grid members within 3 inches of each corner of each light fixture. | |
Heavy Duty Main Tees with cross tee rating below 16 lbs./LF | Required |
Min. 12-gauge hanger wires must be attached to the supporting cross tee within 3 inches of the corner of each light fixture. | |
Supplementary hanger wires for Heavy Duty Main Tees with cross tee rating equal to 16 lbs./LF | Not Required |
Service Applications | Requirements |
Air terminals | |
≤ 20 lbs – positively attached to grid | Required |
21 to 56 lbs – positively attached to grid and two wires to structure (may be slack) | Required |
≥ 57 lbs – directly supported to structure | Required |
Sprinkler heads and other penetration clearance | Min 2" dia. opening or a swing joint |
Cable trays and electrical conduit independently supported and braced | Required |
1. Refers to CISCA installation recommendations for zones 3-4 via ASCE 7.
2. The above information is correct to the best of our knowledge at the date of issuance. Because codes continue to evolve, check with a local official prior to designing and installing a ceiling system. This is only intended as a quick reference.
3. Required for ceilings larger than 1,000 square feet.
4. Where substantiating design calculations are not provided.